華星東方承建的河北省石家莊市晉州市生活垃圾焚燒發(fā)電提升技改項目煙氣凈化工程于2025年08月05號開工建設,于08月27號已安裝完成通過初步驗收。
The FGC system undertaken by HEPT of the waste incineration power generation upgrading project in Jinzhou, Shijiazhuang, Hebei Province, has started construction since 5th. Aug 2025 and has been finished on 27th. Aug to pass the preliminary acceptance.
該項目建設總規(guī)模1000t/d,分兩期實施。一期建設規(guī)模 1×600t/d 機械爐排焚燒爐及余熱鍋爐+1×12MW 抽凝式汽輪發(fā)電機組,二期建設目前預留場地。煙氣凈化采用“SNCR脫硝+PNCR 脫硝+SDA脫酸+干法脫酸(熟石灰)+活性炭噴射吸附+袋式除塵器+ GGH+SGH+SCR脫硝+飛灰輸送、存儲及穩(wěn)定化”的處理工藝。提升技改內(nèi)容包括“SDA+袋式除塵器+飛灰輸送+飛灰再熬合+滲濾液回噴+漿液輸送”,為我司EPC工程。此次技改要求在28天極限工期內(nèi)完成核心設備更新,是繼四川宜賓項目竣工僅兩個月后華星東方迎來的又一重大挑戰(zhàn),并再次改寫了行業(yè)提標技改的完工紀錄!
The total capa of this project is 1,000 tons per day and it will be implemented in two phases. The first-phase includes a 1×600t/d mechanical grate incinerator and waste heat boiler, as well as a 1×12MW extraction condensing steam turbine generator set. Currently, reserved space is available for the second-phase construction. The FGC system adopts the treatment process of "SNCR denitrification +PNCR denitrification +SDA denitrification + dry denitrification (slaked lime) + activated carbon injection adsorption + bag filter + GGH+SGH+SCR denitrification + fly ash transportation, storage and stabilization". The upgrading includes "SDA+ bag filter + fly ash conveying + fly ash re-Chelating + leachate re-injection + slurry conveying", which is an EPC project of HEPT. This technological transformation requires the completion of core equipment updates within a 28-day deadline. It is another major challenge for HEPT just two months after the completion of the project in Yibin, Sichuan. Once again it sets a new record for the completion during of technical upgrading in this industry!
在這場看似不可能完成的挑戰(zhàn)背后,是華星東方無數(shù)的心血與汗水,以及無錫制造中心、宣城制造中心兩個新投建工廠提供強大的后方支持。為了確保項目能夠順利推進,各制造中心全體員工全力保障、加班加點。從設備的整體加工制造,到精細打磨,再到最后的噴漆工序,每一個環(huán)節(jié)都嚴格把關,不容有失。他們深知,自己手中的每一個零件、每一臺設備,都關乎著前方工程的速度與質(zhì)量。
Behind this seemingly unbelievable challenge lies the countless efforts and hard work of HEPT as well as the strong support provided by the two newly built plants, which are the Wuxi Manufacturing Center and the Xuancheng Manufacturing Center. To ensure the smooth progress of the progress, all staff of each manufacturing center have been fully committed to providing efforts and working overtime. From the overall processing and manufacturing of the equipment, to the fine grinding and then to the final painting process, every process has been strictly controlled and no defects are allowed. They are well aware that every component is related to the progress and quality of the project.
值得一提的是,華星東方憑借在裝備制造業(yè)領域50余年深耕制造的專業(yè)積累,實現(xiàn)了設備現(xiàn)場大模塊吊裝這一巨大優(yōu)勢。在傳統(tǒng)模式下,設備可能需要分多次拼接以及現(xiàn)場制作焊接,不僅耗時費力,還容易因現(xiàn)場缺乏先進的加工設備及質(zhì)檢保障等手段造成誤差而影響設備性能和工期。而此次華星東方兩大制造中心將設備在工廠內(nèi)完成大模塊預制及拼裝檢驗,確保萬無一失后直接運輸?shù)浆F(xiàn)場進行吊裝,大大縮短了施工周期,提高了施工效率,同時也保證了設備的整體性能和穩(wěn)定性,使得華星東方得以在極限工期的重重壓力下,有條不紊地推進各項工作,最終順利完成既定任務,為項目的成功交付奠定了堅實基礎。
Another thing worth mentioning is that, with over 50 years of professional accumulation in the equipment manufacturing industry, HEPT has achieved a significant advantage in the on-site hoisting of large modules of equipment. Under the traditional mode, equipment may need to be spliced multiple times and fabricated and welded on site. This not only takes a lot of time and effort but also is prone to defects due to the lack of advanced processing equipment and quality inspection guarantees on site, which can affect the performance of the equipment and the construction period. This time, the two manufacturing centers of HEPT have completed the large module prefabrication and assembly inspection of the equipment in the plants. After ensuring everything was qualified, they directly transported it to the site for hoisting. This significantly shortened the construction period, improved the construction efficiency and also guaranteed the overall performance and stability of the equipment. As a result, HEPT has been able to steadily advance all its work under the huge pressure of the extremely short period of construction . Ultimately, the jobs were successfully completed, laying a solid foundation for the successful delivery of the project.
面對設備交叉作業(yè)、現(xiàn)場施工條件嚴苛等重重困難,華星東方采用了“兩班倒 + 模塊化施工+工廠預制保障”的模式,開展 24 小時連續(xù)作業(yè)。同時,團隊還充分利用 BIM 技術優(yōu)化布局,通過精確的模擬和分析,提前發(fā)現(xiàn)并解決了潛在的設計細節(jié)錯誤,節(jié)省了寶貴時間。正是這種不斷探索、不懈努力的精神,讓華星團隊在原定工期內(nèi)圓滿完成任務,以令人驚嘆的“華星速度”刷新了環(huán)保行業(yè)技改紀錄。
Facing numerous difficulties such as cross-operation of equipment and strict on-site construction conditions, HEPT staff have adopted an innovative model of "two-shift system + modular construction + factory prefabrication guarantee" to carry out 24-hour continuous operation. Meanwhile, the team also fully utilized BIM technology to optimize the layout. Through precise simulation and analysis, they have identified and resolved potential design defects in advance, saving precious time. It is precisely this spirit of continuous exploration and unremitting efforts that enabled the HEPT team to successfully complete the task within the originally scheduled schedule, setting a new record for technological transformation in the environmental protection industry with the astonishing "HEPT Speed".
華星東方在河北省的業(yè)績涵蓋包括:保定一期、二期、衡水、衡水安平、定州、滄州一期、石家莊、石家莊廈能炘、石家莊行唐、唐山曹妃甸、唐山灤州、唐山豐潤、唐山潔城、唐山遷安、承德圍場、保定順平、唐山一期、二期、承德張家口北、廊坊固安、廊坊香河、廊坊三河、邢臺沙河、邢臺威縣、邢臺巨鹿、邯鄲魏縣等多個項目。
The references of HEPT in Hebei Province include: Baoding Phase I, Phase II, Hengshui, Hengshui Anping, Dingzhou, Cangzhou Phase I, Shijiazhuang, Shijiazhuang Xiannengxin, Shijiazhuang Xingtang, Tangshan Caofeidian, Tangshan Luanzhou, Tangshan Fengrun, Tangshan Jiecheng, Tangshan Qian 'an, Chengde Weichang, Baoding Shunping, Tangshan Phase I&II, Chengde North of Zhangjiakou, Langfang Gu 'an, Langfang Xianghe, Langfang Sanhe, Xingtai Shahe, Xingtai Wei County, Xingtai Julu, Handan Wei County, etc.